This project in Bristol City Centre was a bespoke designed heavy duty Rubbish Chute for a demolition company.

It was particularly difficult due to the location of the works being in a highly pedestrianised area of the City Centre.

At 20m high and with 6 openings this Rubbish Chute required spanning across the access point below to maintain access for vehicles into the building.  It took 12 operatives 1 Week on site working at the top and bottom of the Chute.

The job was complete on time and on budget, the chute worked very well for the contractor on this particular project given the nature of the materials that it was being used for.

Another successful job, planned and executed to a high standard.

 

credit credit credit credit credit credit